Barossa-Singapore project (shipment 2)
The Barossa - Singapore project phase 2 is implemented by PPL. The project is from February 23, 2023, to March 1, 2023.
During this period, 2 packages 6702A and 6702B were transported by PPL from Vina-Offshore port to Dong Xuyen port and launched. To carry out the transport and launch of 2 packages, a number of tasks have been performed by PPL, including:
- Gathering manpower and means and equipment at the port.
- Barges docked, adjusted, and moored barges into the harbor.
- Install pump, and pipe... according to plan and conduct pre-ballast for loadout.
- Arrangement of pedestals on barges; assemble trailers; trailer assembly.
- Move the trailer to the parcel's position and tie the package to the trailer.
- Trial lifting and moving the package from Vina-Offshore port to Dong Xuyen port.
- Check pump operation.
- The trailer moves the package to the loadout position and loads the package onto the barge.
All transportation and launching of 2 packages were completed on March 1, 2023. In the coming time, PPL will continue to update the latest information on the progress of the Barossa-Singapore project.