Gia Lai Wind Power Project

27/10/2021
IA LE 1 WIND POWER PLANT
  • Owner: Cao Nguyen 1 Wind Power Development Investment., Jsc
  • Epc: Vinpower Technology and Trading., Jsc
  • PPL’s partner: Megamove
  • PPL’s scope: Transportation for blade
  • The total project cargo: 12/28 turbines
  • The lengthest package: 76.4 m
  • Transport distance: 245 km
    (From Phu My seaport to site)
  • Project time duration: From Jun 2021
Quick view
Although, the time schedule is strict, the transportation route Moving through many different terrains but with the principle of always ensuring the PRESTIGE and bringing the most benefits to customers, plus the inherent internal resources of vehicles as well as staff, Precious Prestige Trading and Logistics One Member Company Limited (PPL) has successfully transported all wind power equipment of the project at the request of the investor, ensuring safe transportation time and quality.