QUANG TRI 1 AMACCAO WIND POWER PLANT
  • Owner: Amaccao Group
  • PPL’s scope: Transportation and customs clearance service
  • The total project cargo: 12 turbines
  • The weight of heaviest package: 103 tons
  • The lengthest package: 76.2 m
  • Transport distance: 245 km
    (From Hon La seaport to site)
  • Project time duration: From June 2021 to August 2021​​​​​​​
Quick view
Amaccao Quang Tri 1 wind power plant is one of the wind power plants with the largest, longest and heaviest equipment among all wind power projects in Vietnam. With the request of progress from the investor along with the characteristics of the rainy and stormy weather of the Central region, especially the conditions of transportation during the outbreak of the disease, it is difficult to carry out transportation for the project, but with modern and newly imported equipment that meets world standards for transporting super-heavy goods and the determination of Precious Prestige Trading and Logistics One Member Company Limited (PPL)'s the Directors Board with  experts, professional and experienced staff, PPL has completed transporting 12 wind power towers of the project within 30 days.

Comments