NHON TRACH 3 AND NHON TRACH 4 POWER FACTORY PROJECT
19/04/2023
Continuing to earn the trust of customers and partners, PPL undertakes logistics activities for Nhon Trach 3 and Nhon Trach 4 Power Plant projects.
Quick view
Services provided by PPL in this project are import clearance and road transportation. The first shipment included 6 40' open-top containers. The road from Ho Chi Minh Port to the project site in Nhon Trach district, Dong Nai.
- From May 6, 2023, to May 10, 2023, PPL transported 4 containers of 40' open-top.
- On May 19, 2023, PPL continued to have 6 containers of 40' open-top.
Transportation distance from Ho Chi Minh City to the project site in Nhon Trach district, Dong Nai.
Below are some pictures of PPL's project implementation.