Lift Test module Kanfa 01 (Phase 2 - April 8, 2022)
10/04/2022
PPL continues the implementation of the Kanfa 2 module loadout project, phase 2 at PV Shipyard.
Quick view
On April 8, 2022, PPL completed the following tasks:
- Complete Lift test Module 01
- Complete the Pre Ballast and arrange the pump to the required Loadout position.
- Carry out the inspection of the winch and pump together with the sides.
Loading out large modules requires experience and precise techniques, so PPL's engineers are very meticulous and thorough in all stages of the project.
Related Posts
New Posts
- PPL successfully performs site-move and load-out of record-breaking 4,000-ton offshore substation topside fabricated by PV Shipyard
- HOLIDAY ANNOUNCEMENT: REUNIFICATION DAY & INTERNATIONAL LABOR DAY (April 30 - May 1, 2025)
- ANNOUNCEMENT OF HUNG KINGS’ COMMEMORATION DAY 2025
- PTSC Thanh Hoa and PPL Sign Strategic Partnership
- INDEPENDENCE DAY HOLIDAY ANNOUCEMENT
- PPL Teambuilding 2024: Uniting Our Strength, Igniting Success!
Comments