Transporting equipment for Tai Tam wind power project in just 28 days

10/11/2021
Tai Tam wind power is one of the wind power projects in Quang Tri that is being expeditiously completed on schedule. Wind power devices are super-long and super-weight devices transported on routes from Hon La port (Quang Binh) to the project located in Khe Sanh, Quang Tri.
Quick view
At the request of the investor, Bao Tin transported 12 sets of pillars including: wings, generators, piers and accessories over a distance of 460 km moving back and forth. Bao Tin has provided 15 convoys of equipment imported from European countries such as Germany and Italy with over 90% new to transport 12 sets of poles of super-heavy wind power equipment to the construction site safely.
Along with the transport convoy of equipment imported from European countries, Bao Tin has established a project board with 60 staff members to operate and direct production at the construction site.
In particular, due to the progress request from the investor along with the typical rainy and stormy weather of the Central region, Bao Tin was determined to complete the transportation of all wind power equipment within 28 days. 
 
Photo: The mountain road in Quang Tri
is characterized by super-heavy equipment and a long, difficult journey. However, with the determination of the leadership and internal resources to provide a convoy of specialized equipment, Bao Tin has successfully transported all wind power equipment to the project on schedule, contributing to the success of the project. success of Tai Tam wind power project.
 
Photo: Wind power propeller weighs thousands of tons
 
The project requires the fastest progress among the projects to be implemented, with a 30-day requirement in the context of the epidemic outbreak that restricts movement, so it is difficult to gather vehicles for the project, plus the I have the means, but I can't deploy it because of the continuous stormy weather. However, with a wealth of experience in the field of logistics, we have centrally coordinated nearly 20 convoys and flexibly coordinated to ensure on schedule while still being safe for the entire project team as well as staff. Wind power equipment and transportation equipment
We have completed transporting the entire project in 28 days, exceeding the time limit, with dangerous weather conditions, limited resource mobilization due to the epidemic context. disease outbreak. But with the spirit of working wholeheartedly for the sake of efficiency for our customers, we have worked day and night, flexibly in each shipping option. Achieving unexpected success is completing the project ahead of schedule set by the investor, this is the pride of Bao Tin in general and the project implementation staff in particular and shows that there is no project. Any logistics can make it difficult for us to Bao Tin.