PPL The journey we have been through
The old year has passed away, when we are welcoming the new year, let’s have a look at an extremely difficult and challenging year. Each member of Precious Prestige Trading and Logistics Company Limited (“PPL”), who was all important, has worked together to finish our job in the most excellent and the fastest way. Having been through a fluctuating year because of the pandemic, but under the guideline of the talented leader with all PPL’s employees and the support, sharing form the partners, customers, we all want to take PPL out to the world.
7 wind-power projects which has built our success in the last year:
1. ĐAKNONG WIND POWER PROJECT
Đak N’Drung 1-2-3 Wind Power Plant
Project owner: Đắk N’rung Đắk Nông-1 Energy One Member Company Limited
Contractor: Sungrow Power Vietnam Co., Ltd.
PPL's partner in this project is Sinovitrans Logistics Co., Ltd. PPL loaded and unloaded at the port 43 wind turbine towers and transported 16 wind turbine towers from Phu My port and Cam Ranh port to the construction site with the heaviest cargo of 106 tons and the longest cargo of 75.7m.
ĐAKNONG WIND POWER PROJECT
2. ĐAKLAK WIND POWER PROJECT
Cu Ne 1-2 Wind Power Plant
Krong Buk 1-2 Wind Power Plant
Project owner: Cu Ne Renewable Energy Company Limited and Krong Buk New Energy Investment Company Limited.
Contractor: China Huadian Company, PPL's partner in this project is CMEC
PPL did customs clearance procedures and transported 73 wind turbine towers from Phu My port and Cam Ranh port to the construction site with the heaviest cargo of 110 tons and the and the longest cargo of 77 m.
ĐAKLAK WIND POWER PROJECT
3. HUONG LINH WIND POWER PROJECT
Huong Linh 3-4 Wind Power Plant
Project owner: Huong Linh 3 Wind Power Company and Huong Linh 4 Wind Power Company
PPL's partner in this project is Rongtua Corp
PPL did customs clearance of goods and transports 19 wind turbine towers from Hon La port to the construction site with the heaviest cargo of 87.7 tons and the longest cargo of 70 m.
HUONG LINH WIND POWER PROJECT
4. KON TUM WIND POWER PROJECT
Tan Tan Nhat – Dak Glei Wind Power Plant
Project owner: Tan Tan Nhat Joint Stock Company
Contractor: China Energy Engineering Group Anhui.
PPL's partner in this project is CMEC, PPL transported 18 wind turbine towers from Phu My port and Quy Nhon international port to the construction site with the heaviest cargo of 114 tons and the longest cargo of 76.5 m.
KON TUM WIND POWER PROJECT
5. GIA LAI WIND POWER PROJECT
Wind Power Plant Iale 1
Project owner: No.1 Highland Wind Power Development Investment Joint Stock Company
Contractor: Vinpower Trading and Technology Company.
PPL's partner in this project is Megamove, PPL transported 12/28 blade-sets from Phu My port to the construction site with the longest cargo of 76.4 m.
GIA LAI WIND POWER PROJECT
6. TAI TAM WIND POWER PROJECT
Tai Tam Wind Power Plant
Project owner and PPL’s partner: Tai Tam Quang Tri Energy Investment Company Limited
PPL transported 12 wind turbine towers from Hon La port to the construction site with the heaviest cargo of 86.9 tons and the longest cargo of 70m.
TAI TAM WIND POWER PROJECT
7. AMACCAO WIND POWER PROJECT
No.1 Quang Tri Amaccao Wind Power Plant
Project owner and PPL’s partner: Amaccao Company
PPL transported 12 wind turbine towers from Hon La port to the construction site with the heaviest cargo of 103 tons and the longest cargo of 76.2m.
AMACCAO WIND POWER PROJECT
In addition to wind power projects implemented in the past year, PPL has also successfully caried out the load-in, load-out and wharves relocation projects, such as:
Relocating QC08 cranes at Tan Vu port, Hai Phong, according to the maintenance schedule of QC08 cranes, weighing up to nearly 700 tons, needing to be relocated from the wharf to the inner yard for maintenance. To fulfill this requirement, PPL used a self-propelled modular transporter (SPMT) and planned in accordance with the procedure to successfully move the QC08 crane.
Relocating QC08 cranes at Tan Vu port, Hai Phong
And right in the last days of December 2021, PPL has successfully loaded out, loaded in the HRSG modules project with 4 modules having the weight of nearly 600 tons / module has been successfully transported and launched from Dong Xuyen port to Shipyard Port.
“After having planned, we had co-operated with the inventor and maritime superintendent to make sure of the operation. We had to use the modern applications to calculate specifically” - Mr. Do Hoang Phuong, Chairman-C.E.O of PPL.
“I highly appreciate the working attitude and the professional way of PPL. The most important thing is the co-operation of the sub-contractors and the contractor, also the other companies while we did these affairs” - Mr. Ly Viet Cuong -Director of HRSG Modules Project.
“The PV Shipyard is the contractor for this project. The PPL was also very professional in providing human resources and devices. The PV Shipyard had also co-operated with PPL, which was very safe. The modules have arrived in PV Shipyard safely” - Mr. Vo Anh Dung – Safety Manager of PV Shipyard.
Loaded out, loaded in the HRSG modules
Achieving these achievements is built on the consensus and solidarity of the entire team of experienced, responsible, and highly specialized human resources experts of PPL under the guideline of the Board of Directors, always towards the principle of professional work, bringing many benefits to customers.
PPL always aspires to improve expertise, reach out to the big sea, not only has practical experience in implementation, but also cooperates with major global partners to affirm its capacity with international contractors in various projects. global events such as joining with CMEC to participate in the Summit on Renewable Energy and Wind Power 2021.
Summit on Renewable Energy and Wind Power 2021
In the past year, PPL did not only endeavor to successfully complete projects, we and our partners across the country unanimously shared difficulties with our compatriots to overcome the pandemic. PPL has donated ventilators to Quang Tri field hospital and vaccinated all staff.
The year 2021 has passed, despite many difficulties, the PPL members have always united to create the strength to build success. Welcome the year 2022, growing faster and stronger.
Related Posts
New Posts
- HOLIDAY ANNOUNCEMENT: REUNIFICATION DAY & INTERNATIONAL LABOR DAY (April 30 - May 1, 2025)
- ANNOUNCEMENT OF HUNG KINGS’ COMMEMORATION DAY 2025
- PTSC Thanh Hoa and PPL Sign Strategic Partnership
- INDEPENDENCE DAY HOLIDAY ANNOUCEMENT
- PPL Teambuilding 2024: Uniting Our Strength, Igniting Success!
- Charity Program Warms Hearts Of PPL in Phuoc Hai Town
Comments