Huong Linh 3 wind power project - Investment adjustment approved

17/03/2022

Mr. Vo Van Hung - Chairman of Quang Tri Province People's Committee has just signed Decision No. 756/QD-UBND approving the adjustment of investment policy, besides approving the investor of Huong Linh 3 wind power plant project.

Quick view

Original approved decision

According to Decision No. 781/QD-UBND signed on April 9, 2019, the Huong Linh 3 Wind Power Plant project was approved for the first time by the People's Committee of Quang Tri province with the investment policy for Huong Linh 3 Wind Power Joint Stock Company. headquartered in Cooc village, Huong Linh commune, Huong Hoa district) as the investor.

The project has a total capacity of 30 MW, with 9 wind turbines, each wind turbine from 3.3 to 3,465 MW. The average electricity output is about 123,329,000 kWh/year. The project is implemented in Huong Linh commune, Huong Hoa district on an area of ​​8ha (excluding land used for the foundation of the line pillars connected to the national power grid, temporary land area for construction). Total investment capital is more than 1,530 billion VND.

The project progress approved in the decision took place from March 2019 to May 2019, making technical design - construction drawings. December 2020 will calibrate, connect and generate electricity.

Adjustments are approved during project implementation

However, in mid-2020, Tan Hoan Cau Corporation had a written request to adjust the investment project. Based on that request, on October 13, 2020, the People's Committee of Quang Tri province issued Decision No. 2946/QD-UBND approving the adjustment of the project investment policy.

In this adjustment, the investment capital for this Huong Linh 3 wind power plant project is adjusted from VND 1,530 billion according to the original plan to VND 1,118 billion.

Then, on March 10, 2022, the People's Committee of Quang Tri province continued to issue Decision No. 756/QD-UBND approving the Huong Linh 3 Wind Power Joint Stock Company to adjust the investor, at the same time approving the investor in the project. judgment.

In this adjustment approval, the land use area is adjusted from the original plan of 8 ha to 9.02 ha. Implementation progress until September 2022 for testing, adjustment and connection.

According to Vietnam Energy Magazine