EFFICIENT RESPONSIBILITIES ON WIND POWER SITES IN QUANG TRI

05/11/2021
Wind power projects in Quang Tri have come to an end when the testing process for commercial operators must be completed before November 1, 2021. In order to meet the progress requirements set out in the past time by the attention of the provincial leaders, the efforts of investors and construction units have so far had 18 wind power projects capable of commercial operation. trade before November 1, 2021.
Quick view
Although the implementation of wind power projects faces many difficulties due to the complicated mountainous terrain, especially the Covid-19 epidemic, which has greatly affected the progress of wind power projects. . However, with the timely attention and resolution of difficulties and obstacles of the leaders of Quang Tri province along with the high determination efforts of investors, construction contractors contributed to completing the progress of the projects. proposed project
Mr. Ha Thanh Trung - Representative of PPL shipping unit said that in order to complete the goals of the projects, experts have made efforts by mobilizing the total force from vehicles, people and all solution. In particular, the use of special super-long-weight vehicles has helped us complete the transportation of wind capacitors on time and according to the plan in the contract signed between the two units.

 

PPL accompanies wind power projects in Quang Tri
Mr. Vu Anh Minh - Director of SCI projects in Quang Tri also highly appreciated the fact that the units have combined the support of the province, the available capacity of SCI and of subcontractors to take advantage of this time. Integrated weather to expedite shipping and installation of equipment. Especially, the combination of working online with EVN agencies and departments to complete the work related to the experiment and the experiment to calibrate enough to energise
According to the report of the Department of Industry and Trade, out of 29 projects For wind power projects approved by the provincial People's Committee, there are 3 projects in the stage of surveying and formulating investment projects; 8 projects are underway to design construction drawings for site clearance, land acquisition and allocation; 18 construction investment projects are capable of commercial operation before November 1, 2021. Specifically, 16 projects have completed the installation of turbines, are currently performing equipment calibration, carrying out procedures related to acceptance test to energize and put into commercial operation with a total capacity of 632MW. 
According to Director of Quang Tri Department of Industry and Trade, Mr. Le Tien Dung, currently, as of October 31, 2021, there are about 16 projects that are 100% COD and 2 projects are capable of COD part of their capacity with COD. The total capacity is expected to be 632MW. The Department of Industry and Trade is coordinating with the Ministry of Industry and Trade to inspect and re-evaluate projects, especially projects of the Ministry of Industry and Trade after appraisal to ensure environmental issues and procedures. ensure according to the approved design, ensure the safety of the operation in the coming time.

With the rush to complete projects on schedule for commercial operation before November 1 this year, it not only shows the determination of investors to enjoy government incentives, but also a commitment to co-operate. Working with businesses of provincial leaders to exploit potential advantages to make Quang Tri soon become an energy center in the North Central region.

Source: Quang Tri Television