Complete loadout module 01 at PV shipyard (Phase 2)

11/04/2022
Update the progress of implementation of Kanfa module loadout project phase 2 at PV Shipyard port.
Quick view

On April 9, 2022, PPL completed the following works:

- Conduct toolbox, unify all work items, things to note before performing loadout.
- Complete Site Moving and Loadout Module 01.
- Unload the trailer from the barge and proceed to receive Module 02.

- Complete Lift test module 02.

- Complete the Pre Ballast and arrange the pump in the required position to serve Loadout Module 02.