Terminal 3 - Tan Son Nhat Int'l Airport

Tan Son Nhat Terminal T3 Project is a national key project invested by Vietnam Airports Corporation (ACV), starting construction at the end of 2022 with a total investment of nearly 11,000 billion VND.

z5393757199748-4cc661b76714c6895fd0ce8675980896-1

Goals & Scope of Work

  • Transported all steel structures serving the construction of Terminal T3 in line with project schedule
  • Executed oversized cargo transportation from ATAD Long An and ATAD Dong Nai factories to the project site
  • Ensured operational safety under urban traffic and high-density transportation conditions
  • Coordinated closely with ATAD and site contractors to maintain installation progress at the project site

Key Challenges

  • Large transport volume within a tight execution schedule
  • Steel structures with oversized dimensions and heavy weight requiring specialized transport solutions
  • Transportation routes passing through urban areas with high traffic density
  • Strict safety and schedule control requirements for a key airport infrastructure project

Solutions & Deployment

  • Mobilized dedicated heavy-haul transportation fleets for steel structure delivery
  • Surveyed and optimized transport methods based on actual road conditions
  • Coordinated operations within designated time windows to ensure traffic safety and project progress
  • Strictly controlled cargo securing, load distribution and transportation safety throughout execution
  • Maintained continuous coordination between operations, site teams and contractors to ensure timely delivery

Project Overview

Investor

Vietnam Airports Corporation (ACV)

Client

ATAD Steel Structure Corp

Transport weight (MT)

ATAD Long An: 1,650+ tons | ATAD Dong Nai: 1,505+ tons

Largest cargo dimensions

~24 m × ~5 m

Execution period

May 2024 - September 2024