Formosa Ha Tinh Steel Plant

du-an-formosa-5

Goals & Scope of Work

  • The logistics project for the Formosa Ha Tinh Steel Complex was implemented to support transportation and customs clearance for large volumes of materials and equipment throughout the construction and operation phases of the project.

  • PPL participated in transportation and customs clearance operations, handling approximately two-thirds of the total construction material volume, equivalent to more than 1,000,000 CBM of cargo.

  • The scope of work included transportation of various cargo types such as construction equipment, containers, bulk cargo, LCL cargo and air freight, combined with customs clearance services to ensure continuous cargo flow and project schedule compliance.

Key Challenges

  • Large cargo volume exceeding 1,000,000 CBM required large-scale logistics coordination and operational capability

  • Multiple cargo categories including containers, bulk cargo, LCL cargo and air freight required flexible transportation solutions

  • Close coordination between transportation and customs clearance operations was necessary to avoid supply chain disruptions

  • High schedule pressure throughout both construction and operation phases of the project

  • Continuous transportation operations along a short route (~30 km) with high delivery frequency

Solutions & Deployment

PPL implemented an integrated logistics solution combining transportation and customs clearance services:

  • Organized flexible transportation systems suitable for each cargo category and operational requirement

  • Conducted efficient customs clearance procedures to ensure timely cargo delivery

  • Coordinated transportation resources continuously to support large cargo volumes over an extended project period

  • Closely monitored project schedules and coordinated between related parties to maintain stable cargo flow

  • Optimized operational processes to improve overall logistics efficiency

Project Overview

Client

Formosa Ha Tinh Steel Corporation

Scope of work

Transportation, Customs clearance

Dimensions

11.8m x 4m x 4.4m

Transport distance

30 km

Quantity

> 1,000,000 CBM

Heaviest/ Longest packages

150 T

Place of Execution

Ha Tinh

Execution period

2014 - now

Notice