Lac Da Vang

web-ldv-3

Goals & Scope of Work

The Block 15-1/05 Lac Da Vang Project is one of the key offshore oil and gas developments in Vietnam, with the main scope involving fabrication and installation of jacket structures for offshore operations.

 

PPL carried out site-move and load-out for the DLV-A-PP Jacket, ensuring the transfer of the structure from the fabrication yard to marine transportation.

 

The scope included moving oversized and heavy structures within the fabrication yard, utilizing SPMT systems for transportation and executing load-out onto a barge in accordance with project technical requirements.

Key Challenges

  • The DLV-A-PP Jacket weighs up to 2,836 tons, requiring specialized transport and load-out solutions

  • Large dimensions and complex center of gravity, demanding precise calculations for load distribution and stability control

  • Load-out operations require high precision to ensure safe transfer from yard to barge

  • Site conditions at the fabrication yard and quay are affected by weather and tidal variations

Solutions & Deployment

  • PPL implemented the site-move and load-out plan based on detailed engineering calculations and close coordination among stakeholders:

  • Utilized SPMT systems to transport the jacket structure, ensuring load distribution and stability during movement

  • Designed a load-out method tailored to yard and quay conditions to ensure safe transfer

  • Closely monitored key technical parameters such as center of gravity, tilt and load distribution throughout execution

  • Ensured coordinated operations between engineering, operations and site teams to maintain schedule and minimize risks

Project Overview

Investor

Murphy Cuu Long Bac Oil Co., Ltd

Client

Petroleum Equipment Assembly & MetalStructure Joint Stock Company (PVC - MS)

Scope of work:

Site-move, load-out

Commodity:

LDV-A-PP Jacket

Weight (MT):

2,836 T

Place of execution

PVC - MS Port (Vung Tau)

Execution time

November 2025