Lac Da Vang

PPL was responsible for providing site-move and load-out services for the DLV-A-PP Jacket weighing 2,836 tons under the Lac Da Vang Project — one of Vietnam’s key offshore oil and gas developments.

Handling and transporting a structure of nearly 3,000 tons requires strong organizational capability, robust technical solutions, and a fully integrated system of specialized equipment. The project was executed with close coordination between engineering and operations teams, ensuring that all movement and load-out activities were carried out safely, accurately, and on schedule.

1-3

Goals & Scope of Work

The Lạc Đà Vàng (Block 15-1/05) project represents a significant milestone in offshore energy development, aimed at optimizing national oil and gas extraction capabilities. As a specialist partner, PPL was entrusted with the critical transportation engineering for the project's primary offshore structure.

Our role was to deliver a seamless, high-integrity heavy-lift solution for the jacket structure, ensuring a flawless transition from the fabrication facility to the designated marine transportation vessel. This project underscores PPL’s core expertise in managing complex logistics for ultra-heavy, out-of-gauge (OOG) assets within high-stakes, time-sensitive industrial environments.

Key Challenges

  • Massive Payload Management: Handling a 2,836-ton jacket required sophisticated load-bearing strategy and specialized heavy-lift equipment to maintain structural safety.

  • Structural Integrity: The complex geometry and non-symmetrical center of gravity necessitated rigorous engineering calculations to prevent stress during the move.

  • Load-Out Precision: The transfer process demanded extreme dimensional accuracy to ensure safe structural alignment between the fabrication quay and the barge.

  • Dynamic Environmental Factors: Operations were subject to strict tidal windows and environmental conditions, requiring precise scheduling and contingency planning.

Solutions & Deployment

  • Advanced SPMT Configuration: Deployed a high-capacity Self-Propelled Modular Transporter (SPMT) system to ensure optimal weight distribution and stability across the entire site-move path.

  • Engineered Load-Out Strategy: Developed a custom transport plan, integrating hydro-ballast calculations and alignment protocols to manage the vessel-to-quay interface effectively.

  • Rigorous Technical Oversight: Implemented real-time monitoring of hydraulic parameters, axle loads, and structural stability throughout the load-out operation.

  • Operational Synergy: Streamlined the collaboration between engineering, technical support, and site operations to mitigate risks, maintain critical path milestones, and ensure project success.

Project Overview

Investor/ PPL's Client:

Murphy Cuu Long Bac Oil Co., Ltd/ Petroleum Equipment Assembly & MetalStructure Joint Stock Company (PVC - MS)

Scope of work:

Site-move, Load-out

Commodity:

LDV-A-PP Jacket

Weight (MT):

2.836T

Notice