Golar Gimi FLNG
Goals & Scope of Work
- Transport and load-out/load-in of modules serving the Heat Recovery Steam Generator (HRSG) system
- Execution of site-move, load-out and load-in operations
- Utilized SPMT/trailer systems for oversized and heavy cargo transportation
- Transportation between Dong Xuyen Port and the Shipyard area
Key Challenges
- Heavy modules requiring strict stability control during transportation and load-out operations
- High precision required during cargo transfer between quay and barge
- Impact from weather and tidal conditions during execution
- Coordination required between transport systems, barge operations and site teams
- Maintaining project schedule within continuous port operations
Solutions & Deployment
- Mobilized dedicated SPMT/trailer systems suitable for heavy cargoControlled technical factors such as center of gravity, load distribution and tilt
- Executed load-out/load-in operations based on actual tidal conditions
- Applied lashing, positioning and safety control throughout transportation
- Ensured close coordination between engineering, operations and site teams to maintain safety and progress
Project Overview
Client
PV Shipyard
Scope of work
Site-move, load-out, load-in
Comodity
4 modules of HRSG
Weight (MT)
500
Dimensions
17 x 8.6 x 25 m
Place of execution
Dong Xuyen Port - PV Shipyard Port
Execution period
24/12/2021 - 30/12/2021