Barossa FPSO (Shipment 1)
Goals & Scope of Work
- Transport and load-out of 02 CO₂ processing skids
- Route: Vina-Offshore → Dong Xuyen Port
- Movement using trailers/SPMT with lifting support
- Load-out onto barge for international marine transport
Key Challenges
- Heavy equipment requiring strict stability and balance control during movement
- Coordination between two port locations
- High precision required during load-out operations
- Synchronization between transport – lifting – barge
- Impact from tidal conditions and port operations
Solutions & Deployment
- Used SPMT/trailer systems suitable for heavy loads
- Applied lifting support for safe movement and accurate positioning
- Executed load-out based on tidal windows
- Controlled key factors such as center of gravity, tilt and load distribution
- Ensured coordination between engineering, operations and site teams
Project Overview
Client
Bolloré Logistics Vietnam
Scope of work
Site-move, load-out
Comodity
2 skids of CO2 Removal Packages: 6701A & 6701B
Weight (MT)
250-357 tons
Place of execution
Vina-Offshore Port & Dong Xuyen Port
Execution time
26/01/2023 - 01/02/2023