Barossa FPSO (Shipment 1)

web-barossa-2-1-1

Goals & Scope of Work

  • Transport and load-out of 02 CO₂ processing skids
  • Route: Vina-Offshore → Dong Xuyen Port
  • Movement using trailers/SPMT with lifting support
  • Load-out onto barge for international marine transport

Key Challenges

  • Heavy equipment requiring strict stability and balance control during movement
  • Coordination between two port locations
  • High precision required during load-out operations
  • Synchronization between transport – lifting – barge
  • Impact from tidal conditions and port operations

Solutions & Deployment

  • Used SPMT/trailer systems suitable for heavy loads
  • Applied lifting support for safe movement and accurate positioning
  • Executed load-out based on tidal windows
  • Controlled key factors such as center of gravity, tilt and load distribution
  • Ensured coordination between engineering, operations and site teams

Project Overview

Client

Bolloré Logistics Vietnam

Scope of work

Site-move, load-out

Comodity

2 skids of CO2 Removal Packages: 6701A & 6701B

Weight (MT)

250-357 tons

Place of execution

Vina-Offshore Port & Dong Xuyen Port

Execution time

26/01/2023 - 01/02/2023