Barossa FPSO (Shipment 3)

PPL continues to implement the Borossa-Singapore Project Phase 3 from April 26, 2023 to May 1, 2023.

1-2

Goals & Scope of Work

  • Transport and load-out of structures serving the CO₂ processing system
  • Route: Vina-Offshore → Dong Xuyen Port
  • Movement using SPMT/trailer systems with lifting support
  • Ensured load-out operations for international marine transportation

Key Challenges

  • Heavy equipment requiring stability control during movement
  • Load-out operations requiring precise coordination between transport systems and barge
  • Limited operating space within the port area
  • Impact from tidal conditions and quay operations
  • Maintaining schedule throughout multiple execution phases

Solutions & Deployment

  • Mobilized dedicated SPMT/trailer systems suitable for heavy cargo
  • Applied lifting support and positioning operations for safe handling
  • Executed load-out operations based on actual tidal windows
  • Controlled technical factors such as center of gravity, load distribution and tilt
  • Ensured close coordination between engineering, operations and site teams to maintain safety and progress

Project Overview

Client

Bolloré Logistics Vietnam

Scope of work

Site-move, load-out

Comodity

02 kiện skid lọc khí CO2: 6703A & 6703B

Weight (MT)

250-357 tons

Place of execution

Vina-Offshore Port & Dong Xuyen Port

Execution time

26/04/2023 - 01/05/2023.