Barossa FPSO (Shipment 3)
PPL continues to implement the Borossa-Singapore Project Phase 3 from April 26, 2023 to May 1, 2023.
Goals & Scope of Work
- Transport and load-out of structures serving the CO₂ processing system
- Route: Vina-Offshore → Dong Xuyen Port
- Movement using SPMT/trailer systems with lifting support
- Ensured load-out operations for international marine transportation
Key Challenges
- Heavy equipment requiring stability control during movement
- Load-out operations requiring precise coordination between transport systems and barge
- Limited operating space within the port area
- Impact from tidal conditions and quay operations
- Maintaining schedule throughout multiple execution phases
Solutions & Deployment
- Mobilized dedicated SPMT/trailer systems suitable for heavy cargo
- Applied lifting support and positioning operations for safe handling
- Executed load-out operations based on actual tidal windows
- Controlled technical factors such as center of gravity, load distribution and tilt
- Ensured close coordination between engineering, operations and site teams to maintain safety and progress
Project Overview
Client
Bolloré Logistics Vietnam
Scope of work
Site-move, load-out
Comodity
02 kiện skid lọc khí CO2: 6703A & 6703B
Weight (MT)
250-357 tons
Place of execution
Vina-Offshore Port & Dong Xuyen Port
Execution time
26/04/2023 - 01/05/2023.