Z189 Platform - Shipbuilding industry

z4629108721731-1547c450c38e768d1daff9de4f02d4f6-1

Goals & Scope of Work

The Z189 Loadout Project was implemented to transport and launch large steel structures serving the shipbuilding industry, preparing for export to international markets.

 

PPL carried out site-move, load-in and load-out operations, including transporting and transferring two platform structures (Platform A & B) from the fabrication area to the quay and executing load-out onto a barge.

 

The scope involved handling oversized and heavy cargo with significant weight:

Platform A: approximately 923.64 tons
Platform B: approximately 950.04 tons

Key Challenges

  • Platform structures weighing close to 1,000 tons per unit, requiring strict control of stability and load distribution

  • High precision required during load-out operations from yard to barge

  • Coordination required between SPMT systems, supporting equipment and barge throughout execution

  • Site conditions at the quay affected by tidal variations

  • Strict safety control required during launching of large structures

Solutions & Deployment

PPL implemented the load-out plan based on detailed engineering calculations and extensive project experience:

  • Utilized SPMT systems to transport the platforms, ensuring load distribution and operational stability

  • Designed load-out and launching methods suitable for quay and barge conditions

  • Closely monitored key technical parameters such as center of gravity, tilt and load distribution throughout the operation

  • Ensured coordinated execution among engineering, operations and site teams to maintain schedule and safety

  • Supervised the entire process to ensure high precision at every stage

The successful execution of the project further demonstrates PPL’s capability in delivering large-scale load-out operations in Vietnam.

Project Overview

Investor

Super Freight

Client

189 One Member Limited Liability Company

Scope of work

Site-move, load-in, load-out

Commodity

Platform A & B

Weight (MT)

~ 1.000 T/platform

Place of execution

Hai Phong

Execution time

August 2023