Dak N’drung Wind Power 1, 2, 3 – Dak Nong
Goals & Scope of Work
Dak N’Drung 1, 2 & 3 wind power projects in the Central Highlands
PPL transported 81 wind power equipment sets (tower, blade, nacelle) from Phu My Port and Cam Ranh ports to the site
Ensured on-schedule delivery in compliance with international safety standards
Key Challenges
Heavy & oversized components (up to 107 tons, 75.7 m length)
Long transport distance (~620 km) from port to site
Mountainous terrain with complex route conditions, weather, and traffic impacts along the corridor
The quaratine time of COVID-19
Solutions & Deployment
Mobilized specialized transport fleet imported from Europe
Developed dedicated transport plans for each oversized component
Executed port handling and route-based delivery strategy
Maintained strict HSE and operational control throughout
Deployed experienced teams for real-time coordination and issue handling
Project Overview
Investor
Sungrow Power Supply Co., Ltd.
Contractor
Sungrow Power Supply Co., Ltd.
PPL's Client
Sinovitrans Logistics Co., Ltd.
PPL provides:
Port handling and transportation
Cargo volume
81 turbines
Heaviest cargo item
107 tons
Most oversized cargo item
75.7 m
Transportation distance
620 km (From Phu My Port to construction site: 338 kmFrom Cam Ranh Port to construction site: 275 km)
Transportation time
From March 2021