Ship Unloader F1000
PPL executed site-move and installation services for the Ship Unloader F1000 system at PTSC Phu My Port, including the transportation, lifting, and positioning of oversized and heavy-lift equipment with a maximum weight of up to 310 tons.
The project falls under port equipment installation with high technical requirements, demanding precise coordination between transportation and installation under restricted space and live port operating conditions.
Goals & Scope of Work
- The Ship Unloader F1000 project was implemented to support cargo handling operations at the port, requiring the installation of large-scale and heavy equipment within a confined working environment.
- PPL participated as the service provider for site-move and installation of oversized and heavy equipment, including receiving, transporting, and positioning the ship unloader system from the staging area to its designated installation location at the port.
- The scope of work included transportation using SPMT systems, coordination of lifting equipment, and execution of installation works with high precision in accordance with project technical requirements.
Key Challenges
- The ship unloader system features a complex structure, large dimensions, and a weight of up to 310 tons, requiring specialized transportation and lifting solutions
- Transportation and installation activities were carried out within an active port environment, with limited space and strict safety requirements
- Close synchronization between transportation, lifting, and installation was required to ensure precise positioning of the equipment
- Execution conditions were affected by weather factors and the port operating environment
Solutions & Deployment
PPL implemented the site-move and installation plan based on detailed engineering calculations and on-site surveys:
- Utilized SPMT systems to transport heavy equipment, ensuring proper load distribution and stability during movement
- Combined with specialized crane equipment to perform lifting and positioning in accordance with technical requirements
- Developed detailed operation planning to ensure safety within the active port area
- Coordinated closely among engineering, operations, and site teams to control progress and minimize risks
Project Overview
Investor/ PPL's Partner:
PTSC Phú Mỹ / Neuero
Scope of work:
Site-move
Heaviest packages:
310T
Results & Effectiveness
The project was successfully executed, with the ship unloader system transported and installed in its designated position, ensuring safety throughout the entire process.
Completion of the project on schedule contributed to the timely commissioning of the system, while further reinforcing PPL’s capability in delivering high technical industrial projects, particularly in the field of heavy lifting and on-site installation of oversized and heavy equipment .